FCX Performance
Pump Repair Tracker
Corrosion Fluid Products Β· Romeoville Shop
Demo mode (no sign-in) Β· Mon, Nov 9Sign in
☎ Take a RequestNew
More

Reports

Pilot Scorecard β€” request to quote, same-day pump-down calls, and requests sent with a data-plate photo

A request counts on the shop day it came in. Weeks run Monday to Sunday.

Loading…

Open Jobs by Age β€” every open job by days since the request came in, as of today (Nov 9, 2026); the date range below doesn't change it

8 open jobs. Open longest: PR-261020-0001 Β· DEMO - Kankakee Fine Chemicals, 20 days.

Since the request came inOpen jobsBarShare
0–7 days450%
8–14 days225%
15–30 days225%
Over 30 days00%
Stage0–7 days8–14 days15–30 daysOver 30 daysTotalOpen in List
New20002
Reviewing10001
Quoted10001
Approved01001
In Shop01001
Ready00101
Shipped00101
All open42208

Customers with the most jobs open over 30 days

None: no job has been open over 30 days.

The List has no age filter: Open in List shows that stage or customer with the oldest jobs at the top.

Jobs received in the range. Days are calendar days; medians unless noted.

Headline Numbers β€” jobs received Aug 11, 2026 – Nov 9, 2026

Set a From date to compare with the period before. Speed numbers are medians in calendar days. 8 jobs imported from the spreadsheet on Nov 9, 2026 are counted in open work only.

  • Requests received0
  • Pump down (red)0
  • Quoted$00 jobs
  • Approved$00 jobs
  • Won (closed)$00 jobs
  • Win rateβ€”0 won Β· 0 lost
  • Return rateβ€”0 of 0 came back
  • First responseβ€”medianTarget: 1 day or less β€” no figure yet
  • To first quoteβ€”medianTarget: 3 days or less β€” no figure yet
  • Customer decisionβ€”medianTarget: 7 days or less β€” no figure yet
  • Shop timeβ€”medianTarget: 10 days or less β€” no figure yet
  • Ready β†’ shippedβ€”medianTarget: 2 days or less β€” no figure yet
  • Received β†’ closedβ€”median

Volume β€” requests received in the range

MonthReceivedPump downQuotedQuoted $ApprovedClosedStill open
2026-11000$0004
2026-10000$0004
All000$0008

Speed (days) β€” medians Β· (n=…) marks a median of fewer than 3 jobs: too few to judge Β· hold days are not taken out of shop time

MonthResponseTo first quoteCustomer decisionShopReady β†’ shippedReceived β†’ closedHold (sum)
2026-11β€”β€”β€”β€”β€”β€”0
2026-10β€”β€”β€”β€”β€”β€”0
Allβ€”β€”β€”β€”β€”β€”0

Outcome β€” from close-outs Β· lost $ = value quoted on lost jobs

MonthWonWon $LostLost $Win rateLost reasons
2026-110$00$0β€”β€”
2026-100$00$0β€”β€”
All0$00$0β€”β€”

Returns β€” jobs linked back to an earlier repair

MonthReturnsReturn rateReasons
2026-110β€”β€”
2026-100β€”β€”
All0β€”β€”

Repeat Failures β€” the same pump (serial number) back within 90 days of its last job here

0% of the jobs received in the range were possible repeats (0 of 8). Days are counted from the day the earlier job shipped (or closed).

No possible repeats in this range.

Failure Causes β€” repaired jobs closed since Aug 11, 2026, from the close-out's failure codes

No jobs were closed as repaired in this range.

Time in Each Stage β€” jobs that left each stage Aug 11, 2026 – Nov 9, 2026

No job left a stage in this range. Days are calendar days with time on hold taken out. β€œ8 in 10 within”: that many of the jobs left the stage within this many days. Targets are the board's normal time for the stage. Last period means the same number of days just before: May 12, 2026 – Aug 10, 2026. β€œIn this stage now” is as of today and isn't in the medians.

StageJobs that leftMedian days8 in 10 within (days)Target and last periodIn this stage nowLongest so far (days)
New0β€”β€”β€”2β€”
Reviewing0β€”β€”β€”1β€”
Quoted0β€”β€”β€”1β€”
Approved0β€”β€”β€”1β€”
In Shop0β€”β€”β€”1β€”
Ready0β€”β€”β€”1β€”
Shipped0β€”β€”β€”1β€”
On hold (taken out of the stages above)0β€”β€”β€”0β€”

Quote Pipeline β€” each job's latest quote (revisions replace the quote before), sent Aug 11, 2026 – Nov 9, 2026

5 quotes for $32,075; 1 is still waiting. The approval rate counts approved quotes out of the ones answered (approved, declined, or no answer). Last period means the same number of days just before: May 12, 2026 – Aug 10, 2026.

  • Quoted$32,0755 quotesUp $32,075 from last period (was $0) β€” better
  • Approved$27,2254 quotesUp $27,225 from last period (was $0) β€” better
  • Declined$00 quotesSame as last period ($0)
  • Still waiting$4,8501 quote
  • Approval rate (quotes)100%4 of 4 answered quotesNo figure for last period
  • Approval rate (dollars)100%$27,225 of $27,225 answeredNo figure for last period
  • Sent to answerβ€”median, approved or declinedNo figure for last periodTarget: 7 days or less β€” no figure yet

No quote has been waiting more than 7 days.

Where it standsQuotesDollarsShare of dollars
Approved4$27,22585%
Declined0$00%
No answer (expired, or job closed)0$00%
Still waiting1$4,85015%
All5$32,075100%

Why quotes weren't approved

None: no quote in this range was declined or went unanswered.

The decline reason the customer or the team picked; for a quote that expired or was still waiting when its job was closed, the close-out's loss reason.

Biggest quotes still waiting

JobCustomerQuote #SentWaitingAmount
PR-261103-0001DEMO - Lakeshore Specialty ChemNov 54 days$4,850

Request Form Drop-Off β€” people who started the customer request form, how far they got, and where they left

A visit counts on the day it was started. Started = answered at least one question.

Loading…

Customer Ratings β€” what customers answered to β€œHow did we do?” on their closed jobs

A rating counts on the day the customer first sent it.

Loading…